Tanzania's PPP Pipeline Reaches 129 Projects as the State Looks to Partnerships for TZS 170 Trillion of a TZS 477 Trillion Plan
Only 9 of the 129 projects are in implementation and 93 are still at concept or pre-feasibility stage, showing how far the pipeline has to travel to meet the Fourth Five-Year Development Plan's financing target.

Tanzania's Public-Private Partnership Centre (PPPC) had 129 projects in its pipeline by July 2026, but only 9 had reached implementation, according to TanzaniaInvest's report on the centre's first newsletter, an August 2026 issue. Another 3 are in negotiation, 3 in procurement and 21 in full feasibility study, while 44 are at pre-feasibility and 49 at concept-note stage. That leaves 93 projects, or 72% of the pipeline on Native Media's calculation, at the two earliest stages. The centre has also identified 410 potential projects across 26 regions and 184 local government authorities.
The pipeline matters because of what the state is asking of it. The Fourth Five-Year Development Plan (2026/27 to 2030/31) needs TZS 477 trillion, about $181 billion at roughly TZS 2,640 to the dollar (Native Media's conversion). TanzaniaInvest reports that the private sector is expected to provide about TZS 334 trillion, or 70%, of which TZS 170 trillion, about $64 billion, would come through PPPs. The Citizen reported the same three figures in March 2026.
The TZS 170 trillion is an estimate rather than a tally of identified deals. PPP specialist Bravious Kahyoza, writing in the Daily News in March 2026, derived it by applying a historical 51% PPP share to the private sector's TZS 334 trillion, which works out at about TZS 34 trillion a year. Kahyoza told The Citizen that Tanzania allocates about TZS 2 billion to project preparation, and the newspaper noted that the international guideline of about 2% of expected investment would imply roughly TZS 3.4 trillion.
Named projects in the wider pipeline include the $1.4 billion rehabilitation and operation of TAZARA, the Dar es Salaam Bus Rapid Transit system, the Dar es Salaam port concessions, the Kariakoo One-Stop Business Complex and the Kibaha-Chalinze-Morogoro Expressway. PPPC Executive Director David Kafulila confirmed the 129 total. The centre, legally established in 2014 under a 2010 act, became fully operational only in January 2024, and TanzaniaInvest reports that it has since trained 5,127 people from local authorities, government agencies and private companies.
Why it matters
This section is Native Media's analysis. For investors, the stage breakdown is more useful than the headline count: the near-term opportunity is the 15 projects from implementation through procurement and the 21 in full feasibility, not the longer list behind them. For the government, the question is conversion, since the plan's financing arithmetic assumes that private partners sign and fund deals within five years. The numbers to watch are how many projects move from feasibility to procurement, and whether preparation funding rises. The data is as of July and the PPPC newsletter itself was not read directly, so readers should check the centre's own publications for exact figures.
Sources
- PPPC newsletter: 129 projects, TanzaniaInvest, (2 November 2026; data as of July 2026)
- Tanzania's PPP allocation too small to make meaningful impact, say experts, The Citizen (Tanzania), (12 March 2026)
- How PPP dialogue series will mobilise trillions for development plan, Daily News (Tanzania), (3 March 2026)
Related
Related research, podcast episodes will be linked here. See African Intelligence and Research & Publications.